How to Calculate Extension of Time in Construction Projects?

2 Responses to “How to Calculate Extension of Time in Construction Projects?”

  • Santa Barbara:

    you should put it in Microsoft Project and mess with it through there. It will allow you to increase or decrease the finish dates based on the current progress and milestones.

  • kayak:

    I use the CPM method. An extension of time is normally only granted if the element(s) of work affected are on the critical path and the delay/potential delay is through no fault of the contractor.

    The better software programs will easliy show the impact/cost of a critical path work item slippage

Leave a Reply



hogan outlet hogan outlet online louboutin pas cher louboutin pas cher tn pas cher nike tn pas cher nike tn pas cher nike tn pas cher nike tn pas cher nike tn pas cher nike tn pas cher nike tn pas cher air max pas cher air max pas cher air max pas cher air max pas cher air max pas cher air max pas cher golden goose outlet golden goose outlet golden goose outlet golden goose outlet golden goose outlet golden goose outlet